Client : PTT Public Company Limited

PTT Oil and Gas (Rayong) would like to repair existing water proofing at roof of CCR5, CCR3, GSP#3 and Central substation building with Pure Poly Urea system. Project period is June 2021 to Dec 2021 // Contract amount : 16,000,000 Baht

Our responsibilities is as following details;

1. Execute project with safety management policy for working in hazardous area.
2. Provide JSA , method statement and dust protection
3. Do existing surface preparation (polish, repair and finishing
4. Supply and install for primer and pure poly urea coating
5. Provide inspection and testing as manufacture' standard procedure.
6. Provide final document.